Construction took place within the 2 level Blue Parking Garage and 5 level Orange Parking Garage.
The scope in the Orange garage consisted of concrete beam repairs, overhead repairs and post-tension cable repair
The blue garage scope of work consisted of metal decking stair replacement and conduit relocation which included concrete removal and replacement, metal pan decking fabrication, removal and replacement and conduit removal and relocation
Work was completed for the annual garage restoration program around the mall property.