Grant Park North Triple Basin Replacement

Grant Park North Triple Basin Replacement

Job Location

25 N. Michigan Ave., Chicago, IL

Start Date

03/20/2023

End Date

08/28/2023

Project Value

$ 230,000

Engineer/Architect

BTR Engineering and Sentinel Group

Owner

NEXT Realty

Case Study

Two level underground garage underneath Michigan Ave and Millennium Park.

  • Scope of work consisted of removal and replacement of existing triple basin and pump system to replace with larger capacity system
  • Work included concrete removal and replacement, excavation, plumbing installation of basins, piping and pump system
  • Golf Construction coordinated with Poli Contracting and Sentinel Group to retrofit new equipment into the existing vaults and lay out