Grand Avenue Parking Garage – Repairs and Preservation

Grand Avenue Parking Garage – Repairs and Preservation

Job Location

613 N. Plankinton, Milwaukee, WI

Start Date

09/01/2022

End Date

07/01/2023

Project Value

$ 368,000

Engineer/Architect

WGI

Owner

Interpark, LLC

Case Study

5-Story Parking Structure that is made up of four floors that are post tension and the roof level is precast concrete.

  • Work involved 1,010 Square Feet of precast full depth concrete repair
  • 1,285 Square Feet of Post Tension topside slab repair
  • 170 Square Feet of Post Tension full depth repair, stair tread repairs
  • 1 ton of supplemental reinforcing for slab repairs
  • 285 Lineal of joint sealants, expansion joint replacement
  • Removal of 280-wheel stops, and 13,000 Square Feet of new traffic bearing membrane