City of Des Moines – Parking Garage Repair Program
City of Des Moines – Parking Garage Repair Program
Job Location
400 Grand Avenue, Des Moines, IA 830 7th Steet, Des Moines, IA
Start Date
07/01/2019
End Date
05/01/2020
Project Value
$ 1,534,000
Engineer/Architect
Walter P. Moore and Associates, Inc.
Owner
City of Des Moines
Case Study
Grand Avenue Parking Garage is a 7-Story Precast structure. The 7th Street Parking Structure is a 6-Story Post Tensioned Garage. The repairs included in both garages were:
3,850 Square Feet of concrete topping repairs
88 Square Feet of partial depth floor repairs
580 Square Feet of overhead concrete repairs
160 Square Feet of Beam Repairs
60 Square Feet of wall repairs
170 Square Feet of grout pocket repairs
150 Square Feet of column repairs
25 Corbel repairs
2,000 Lineal Feet of expansion joint seal replacement
2,240 Lineal Feet of crack repairs
23,500 Lineal Feet of joint sealant replacement
108,000 Square Feet of traffic coating replacement